If Labour Cost Variance is 1386 A Labour
Yield Variance is 378 A and Labour Mix
Variance is 42 R then Labour Rate
Variance would be
1,764 A
1,050 A
1.344 A
336 A​

Answers

Answered by rajalaxmi08052007
0

Answer:

366

Step-by-step explanation:

is the answer of this question

Answered by gunjanbaidyasl
0

Answer:

The Labour Rate Variance  will be 1050 (A).

Step-by-step explanation:

To find: Labour Rate Variance  (LRV)

Given,

Labour Cost Variance = 1386 (A)

Labour Yield Variance  = 378 (A)

Labour Mix Variance = 42 (R)

Concept -

Labour Cost Variance = Labour Rate Variance + Labour Mix Variance

                                       + Labour yield Variance

Thus,

Labour Rate Variance = Labour Cost Variance - Labour Mix Variance

                                       - Labour yield Variance

⇒ Labour Rate Variance  = 1386 (A) - 42 (R) - 378 (A)

Labour Rate Variance  = 1050 (A)

The Labour Rate Variance  will be 1050 (A).