To find: Labour Rate Variance (LRV)
Given,
Labour Cost Variance = 1386 (A)
Labour Yield Variance = 378 (A)
Labour Mix Variance = 42 (R)
Concept -
Labour Cost Variance = Labour Rate Variance + Labour Mix Variance
+ Labour yield Variance
Thus,
Labour Rate Variance = Labour Cost Variance - Labour Mix Variance
- Labour yield Variance
⇒ Labour Rate Variance = 1386 (A) - 42 (R) - 378 (A)
⇒ Labour Rate Variance = 1050 (A)
The Labour Rate Variance will be 1050 (A).