Question 31 3 Hindi
? In a slab culvert, the false
work is measured in:
Options (Marks: 1
(Tap/Click on option
Option 1
0 Number
Option 2
B Running meter
Option 3
o Kg
Option 4
0 Sq.m
Answers
Answered by
0
Answer:
option b running meter or multimeter
Answered by
0
Answer:
In a slab culvert, the falsework is measured in meters.
Explanation:
The culvert mainly consists of abutment, wing walls, arches or desk slabs, parapet, and foundation.
Floor pitching from inside the culvert in the bed of drain may or may not be provided, it depends on the soil condition and flows velocity of the stream water.
The slab culverts are constructed for a span of a maximum of 2.5 m in width. To construct the slab culvert, a stone or R.C.C slab is directly placed over the simply supported beam on piers or abutments.
These slabs form a superstructure over the culvert. The parapet and wing walls are also provided in this culvert, similar to the permanent bridge.