QUESTION 4
+5 Marks
10 workers can complete a job in 20 days. After how many days should 5 workers leave so that
the job is completed in 25 days?
Answers
Answered by
4
Answer:
10 workers complete a job in 20 days..
if one person had to complete the job, it would take him 10*20 = 200 days...
Now for the task to be finished in 25 days... the total no of workers should be = 200/25 = 8
Answered by
0
Answer:
15 days.
Step-by-step explanation:
Total Work = 10 * 20 = 200
let x be the number of days after 5 workers leave so we get,
( 25 - x ) * 5 + 10 * x = 200
125 - 5x + 10x = 200
5x = 200 - 125
x = 75 / 5 = 15
Hence, After 15 days the 5 workers leave.