Question 9:- Tanu Ltd. uses predetermined overhead rate of Rs. 15 per labour hour, the actual
overhead cost is Rs. 85,000 and actual labor hour are 5,750. The under or over absorption of
overhead is:
a) Rs 1,250 (over)
b) Rs 1,250 (under)
c) Rs 1,000 (over)
d) Rs 1,000 (under)
Answers
Answered by
2
Explanation:
Actual rate per hour = overhead cost is Rs. 85,000/actual labor hour are 5,750
Actual rate per hour= 14.78 per hour
under absorption of overhead = (15-14.78)*5750
under absorption of overhead =1265