Question:
A, B and C can do a piece of work in 24, 30 and 40 days respectively. They start the work together but C leaves 4 days before the completion of the work. In how many days is
the work done?
Choose one
B. 14 days
A. 15 days
C. 13 days
D. 11 days
Answers
Answered by
1
Here You want to take the HCF of these days
As C left 4 days before u should take 40-4 = 36
HCF of 24,30,36
You will get the answer as ⁶
Answered by
1
Step-by-step explanation:
- option D is correct A =24 days , B= 30 days , C=40 days ,[LCM= 120] one day they can produce 12 units of work ,. total work =120 units ,. however 4 days before completion c leaves which means a plus b work for 4 days alone producing 9 units per day 6 units. therefore work completed by A-B-C[120 -36] 84 units A+B+C work for 7 days producing 84 units and a + b work for 4 days producing 36 units total 7 + 4 = 11 days therefore the answer is 11