Math, asked by hariprasad7825, 18 days ago

Question: A can finish a piece of work in 48 days. He worked alone for 18 days anlone then B joined him and remaining work completed in 18 3/4 days then find how many days B alone can complete the work?

Answers

Answered by student8961
0

Step-by-step explanation:

Work done by A in 48 days = 1 part

∴, " " " " " 1 day = 1/48 part

∴, " " " " " 18 days = 1/48 X 18 part = 3/8 part

∴, Work left = 1 - 3/8 part = 5/8 part

Work done by A and B together in 18 3/4(i.e. 75/4) days = 5/8 part

Work done by A and B together in 1 day= (5/8 ÷75/4)part = 1/30 part

A's one day work = 1/48 part

Thus, work done by B alone = (1/30 - 1/48)part = 15/48 part

Hence, no.of days needed by B to complete the work = (1÷15/48)days = 48/15 days = 3 3/15 days = 3 1/5 days.

Similar questions