QUESTION IS IN ATTACHMENT
Answer both in detail plzz
Attachments:
Answers
Answered by
1
(43)
3(8M+6B) = 15M+30B
24M-15M = 30B-18B
9M = 12B
M/B = 4/3
Total work = 34(8*4+12*3) = 34*48 units .
To done this work in 17 days . we need M =
= 34*48/3*17 = 32M (Ans.)
(Next question try yourself first , if you face problem ask again)