Math, asked by mabupeeravnb, 6 months ago

Question Type : Multiple Choice
Marks For Correct Answer:
2.00
Negative Mark:
0.50
Question No. 4
A large generator is delivering power 1.0 pu power to an infinite bus through a transmission network. The maximum powers which can be transferred for pre-fault, fault and post-fault
conditions are 1.8 pu, 0.4 pu and 1.3 pu respectively. Then the critical clearing angle is degrees.
51.5
59
55.5
53.5​

Answers

Answered by Anonymous
10

Answer:

53.5 is the answer ohk

hope it helps you