Question 3
Sania can finish work in 17 days and Mirza can do the same work in 85 days. Mirza
worked for 10 days and left the job. In how many days, Sania alone can finish the
remaining work?
Answers
Answered by
0
Answer:
sorry I cant understamd question 1
Answered by
0
Concept:
Unitary method is a method to compare the two numbers in their unit value.
Given:
We are given that:
Sania can finish a work in 17 days.
Mirza can do it in 85 days.
Mirza left job after 10 days.
Find:
We need to find the number of days that Sania will take to complete the remaining work.
Solution:
Let the total work be 1.
Work done by Mirza in one day = 1 / 85.
Work done by Mirza in 10 days = 10 / 85 = 2 / 17
Work left = 1 - 2 / 17
= 15 / 17
Work done by Sania in 1 day = 1 / 17
Number of days that Sania can complete work = 15 / 17 ÷ 1 / 17 = 15 days.
Therefore, Sania will take 15 days to complete the remaining work.
#SPJ1
Similar questions
Environmental Sciences,
1 month ago
Math,
1 month ago
Hindi,
2 months ago
Computer Science,
2 months ago
Computer Science,
10 months ago
English,
10 months ago
Math,
10 months ago