Math, asked by lekhaconst1, 6 hours ago

Rahul and Sachin can complete a work in 60 days and 45 days respectively. Rahul starts working with 120% of his capacity and Sachin with 80% of his capacity. In how many days will they complete 75% of the work if they work together?​

Answers

Answered by uchandra52
8

Answer:

Step-by-step explanation:

i

Answered by aryanagarwal466
4

Answer:

They both will complete work in 19.85 days.

Step-by-step explanation:

It is given that Rahul can complete a work in 60 days.

Sachin can complete a work in 45 days.

Taking LCM, we get
LCM of 60,45=180

There are 180 units of work.

Efficiency of Rahul is 180/60=3

Efficiency of Sachin is 180/45=4

Their combine one day of work =1.2(3)+0.8(4)

=6.8 units.

75% of work is 0.75*180=135 units.

They both will work combinely with given efficiency, they will complete work in 135/6.8=19.85 days.