Math, asked by nazafathima303, 6 months ago

rahul can complete a job in 16 days and manish can complete the equal job in 18 days for some reason manish work for 9 days and left the job. Now in how many days Rahul can complete the remaining job?
a) 5days b) 6days c) 7days d) 8days​

Answers

Answered by Anonymous
7

Step-by-step explanation:

There are three methods to solve this problem.

Method-1 Fraction Method

A completes the work in 30 days -> In 1 day he completes 1/30 part of job.

B completes the work in 20 days -> In 1 day he completes 1/20 part of job.

Work done by A & B both in 1 day= 1/30 + 1/20

=(20+30)/(20x30) = 5/60 = 1/12

Let both A & B workd for 'x' days.

Work done by them in x day = x/12

Remaining work = 1-x/12 ………(1)

This remaining work is done by A alone in 5 days.

Hence,

Work done by A in 5 days = Remaining work

5/30 = 1-x/12 …. From (1)

x/12 = 1–1/6

x = (5x12)/6

x=10

Total number of days to complete work = 10+5 = 15 days

Method-2 LCM Method

Let the total units of work be LCM(30,20)=60

A does 60/30 = 2 units per day work

B does 60/2 = 3 units per day work

Together they do (2+3)=5 units of per day work.

Let say both of them worked for x days.

Work done by them in x days = 5x

Remaining work = 60–5x

This remaining work done by A alone in 5 days

Hence,

5*(A's work per day)= 60–5x

5*2=60–5x

x=10

Total number of days taken to complete the work = 10+5 = 15 days

Method-3 Percentage Method

Let the total work be 100%

A does 100/30 = 3.33% work in 1 day

B does 100/20 = 5% work in 1 day

Both A & B do (3.33+5)=8.33% work in 1 day

Let say they worked for 'x' days

In x days the complete x*8.33% work.

Remaining work = 100%-x*8.33%

This remaining work completed by A alone in 5 days

Work done by A in 5 days = 5*3.33%= 16.66%

Hence,

Remaining work = work done by A in 5 days

100 - x*8.33%=16.66%

x*8.33% = 100%–16.66%

x*8.33% = 83.33%

x = 83.33/8.33

x=10 days

Total number of days taken to complete the work = 10+5 = 15 days

Similar questions