Math, asked by sehatrakhri400, 3 months ago

Rahul can do a piece of work in 10 days and simran can do it in 15 days. How long will they take to complete it if they work together?
a. 6 days
b. 5 days
c. 4 days
d. 3 days​

Answers

Answered by annustudio101
0

Step-by-step explanation:

How long will they take to complete it if they to complete it if they work together?

They will take 6 days to complete the work if they together.

Answered by SachinGupta01
0

QUESTION :-

Rahul can do a piece of work in 10 days and simran can do it in 15 days. How long will they take to complete it if they work together?

Time taken by Rahul to finish the work =10 days.

Work done by Rahul in 1 day = 1/10

Time taken by Simran to finish the work = 15days.

Work done by Simran in 1 day = 1/15 days.

Work Done by Rahul and Simran in 1 day = 1/10 + 1/15

= 3+2/30 = 1/6

So, Thus Taken by both to finish work = 1 ÷ 1/6 = 6 days.

So A option is Correct.

Similar questions