Raj does a work in 5 days while Salim does the same work work in 2 days if they work together in how many days will they complete the work
Answers
Answered by
2
Answer:
Salim takes 8 days to finish a piece of work. Manoj takes 12 days to finish the same piece of Work. Raj works twice as fast as Salim. How many days will all three of them together take to finish the same piece of work ?
A) 2311
B) 3813
C) 3913
D) 2913
E) 2211
Correct Answer:
E) 2211
Description for Correct answer:
Salim takes to complete the work = 8 days
Manoj takes to complete the work = 12 days
Raj takes to complete the work = 82 = 4 days
Required days to complete the work by all of the together = 8x12x4(8x12)(12x4)(8x4)
= 8x12x496+48+32
= 2 211
Answered by
17
Answer:
Raj does work in 5 days
so in 1 day he can do 1/5 work
Similarly Salim in 1 day can do 1/2 work
So in 1 day both can do( 1/5) + (1/2) = 7/10 work
So for full work they will take 10/7days