Rajan can do a job in 60 days.

(i)How much of the job will he be able to finish in a day?

(ii)How much of the job will he be able to do in 36 days?

(iii) In how many days will he do 2/5 of the job?

Answers

Answered by gokulbiologylover
7

in one day he can do 1/60 of work

in 36 days1/60×36 he can do 3/5 of work

2/5×60=24days he can able to do 2/5of work in 24 days

Answered by Anonymous
3

Step-by-step explanation:

in 36 days 1 / 60 × 36 he can do 3 / 5

in one day he can do 1 / 60 of work