rajan can do a piece of work in 24 days while Amit can do it in 30 days in how many days can be completed if they work together
Answers
Answered by
5
Work done by Rajan in one day=1/24
Work done by Amity in one day=1/30
Work done by Amit and Rajan=1/24+1/30
=(30+24)/720
=54/720
=3/40
=13.33days (approx)