rajan can do piece of work In 24 days while while amit can do it in 30 days . in how many days can they complete it if they work together
Answers
Answered by
2
Answer:
Add 24 and 30
24+30=54
ans: In 54 days rajan and amit can do 2 piece of work .
opipr2974:
you fool if they work together it will complete fast
Answered by
37
Number of days Rajan takes to do a piece of work =24 days.
Number of days Amit takes to do a piece of work = 30 days.
Work done by Rajan and Amit together in 1 day = Work done by Rajan 1 day + Work done by Amit in 1 day
LCM of 30 and 24 = 120