Rajan is thrice as effictive as ravi and takes 10days less to do a piece of work than Ravi to do the same piece of work. In how many days can ravi alone finish the whole work
Answers
Answered by
0
Answer:
RAVI= 5 days and RAJAN= 15 days
Step-by-step explanation:
LET'S TAKE RAJAN AS A AND RAVI AS B
B=3A
=A+10
so,
3A=A+10
2A=10
A=5
A takes 5 days; B takes 3A, or 15, days i.e. rajan takes 5 days and ravi takes 15 days.
Answered by
0
Let efficiency of Ravi be x
Then Rajan's efficiency=3x
Time is indirect to efficiency so Ravi takes 3t and Rajan take t time
3t-t=10
t=5days
So Ravi takes 15 days to complete the work