Rajat takes 12 days to paint his room if he
works 4 hours a day. How many days will
he take to finish the painting if he works 6
hours a day?
Answers
Answered by
4
Answer:
*8 days*
Step-by-step explanation:
4×12=48hrs
48hrs
--------
6
=8
Answered by
5
Rajat takes 12 days to paint his room if he
works 4 hours a day. How many days will
he take to finish the painting if he works 6
hours a day?
anwer:8
why?
12 x 4 = 48
48hrs
--------
6
=8