Math, asked by arundhatipopatmali, 7 hours ago

Rajesh can build a wall alone in 20 days and Suresh alone can build it in 15 days. If Rajesh and Suresh works together, in how many days they can finish the wall ? ​

Answers

Answered by sahananeel07
1

Answer:

20 days

Step-by-step explanation:

Answered by geetasahani
1

Answer:

Rajesh can build the wall in 20 days

1 day = 1/20 of the wall

Suresh can build the wall in 15 days

1 day = 1/15 of the wall

together they can build the wall in

1/20+1/15 days

= 7/60

Hence they together can complete the wall in 60/7=8.5 or 9 days

Step-by-step explanation:

Hoped my answer helped you and mark me as BRAINLIEST