rajesh can complete a job in 18days.rohit is 50% more skilled than rajesh.find the total time taken to do the same job when they both work together
Answers
Answered by
0
Given: rajesh can complete a job in 18days.rohit is 50% more skilled than rajesh.
To find: the total time taken to do the same job when they both work together
Solution:
rajesh can complete a job in 18days
=> rajesh's 1 day work = 1/18
rohit is 50% more skilled than rajesh
=> Rohit's 1 day work = 1/18 + (50/100)(1/18)
= (1/18)(3/2)
= 1/12
Both together 1 day work = 1/18 + 1/12
= ( 2 + 3)/36
= 5/36
the total time taken to do the same job when they both work together
= 1/(5 /36)
= 36/5
= 7.2 Days