Math, asked by nitrogeneous7091, 1 year ago

Rajesh can complete some work in 42 days while shillpa the same work in 7 days they started together and when the work half complete shilpa fell ill and Rajesh had to finish the remaining work how long did it take to complete

Answers

Answered by RenatoMattice
7

Answer: Rajesh need 24 days to complete the work.

Step-by-step explanation:

Since we have given that

Total number of days in which Rajesh can complete the work = 42 days

Total number of days in which Shilpa can complete the work = 7 days

L.C.M. of 42 and 7 = 42 = Total units of work done

Work done by Rajesh is given by

\frac{42}{42}=1\ unit

Work done by Shilpa is given by

\frac{42}{7}=6\ units

When half of the work complete Shilpa fell illl and Rajesh had to finish the remaining work:

Amount of half work done by them is given by

\frac{42}{2}=21

Half work done by both of them:

Number of days they will take to complete the half work is given by

\frac{21}{1+6}=\frac{21}{7}=3\ days

Remaining work done by  Rajesh

Number of days Rajesh needed to complete the remaining work is given by

\frac{21}{1}=21\ days

Total number of days Rajesh would take to complete is given by

21+3=24\ days

Hence, Rajesh need 24 days to complete the work.