Math, asked by taiba6553, 1 year ago

Rajesh can finish his work in 25 days working 8 hours a day. If he want to finish the same work in 20 days how many hours should he work

Answers

Answered by swimchar25
1
If he wants to finish in 20 days Rajesh has to work 10 hours a day.