Raju alone can do a piece of work in 10 days and manju alone can do it in 12 days.They undertook to do it for 4800. With the help of anand,they completed the work in 5 days.Then the amount paid to raju and anand respectively is
Answers
Answer:
Step-by-step explanation:
Given : Raja and manju were paid Rs.4800 for a work which Raju alone can do in 10 days and manju alone in 12 days. They finished the work in 5 days along with anand
To Find : Amount paid to raju & anand
Solution:
Raju alone can do in 10 days
Raju 1 day work = 1/10
Raju 5 days work = 5/10 = 1/2
Raju was paid = (1/2) * 4800 = Rs 2400
Manju alone can do in 12 days.
Manju 1 day work = 1/12
Manju 5 days work = 5/12
Raju + Manju 1 day work = 1/2 + 5/12
= (6 + 5 ) /12
= 11/12
Anand work = 1 - 11/12 = 1/12
Anand was paid = (1/12) *4800 = 400 Rs
Learn More:
in two days a b and c together can finish 1/2 of a work and in another ...
https://brainly.in/question/2815968
A, B and C working separately can do a work in 2, 3 and 4 days ...
https://brainly.in/question/8205266
A,b,c can do a piece of work in 150 days,75 days,75/2 days ...
https://brainly.in/question/8268307