Raju can do 25% of a piece of work in 4 days. How long would he take to do 5 times the work

Answers

Answered by nrithyasree20
1

Answer:

120 days.

Step-by-step explanation:

It takes him 4 days to do 1/4 of the work, so it would take him 4*4= 24 days to complete the entire piece of work.

So to do 5 times that work it would take him 24*5 days = 120 days.