Math, asked by muleshireesha, 1 year ago

Raju can do a piece of work in 10 days, Vicky in 12 days and Tinku in 15 days. They all start the work together, but Raju leaves after 2 days and Vicky leaves 3 days before the work is completed. In how many days is the work completed?

Answers

Answered by TooFree
2

Answer:

7 days


Step-by-step explanation:

Raju can do the work in 10 days

1 day = 1/10 of the work


Vicky can do the work in 12 days

1 day = 1/12 of the work


Tinku can do the the work in 15 days

1 day = 1/15 of the work


Find the amount of work done in the first 2 days:

1 day = 1/10 + 1/12 + 1/15 = 1/4

2 days = 1/4 x 2 = 1/2 of the work


Find the amount of work Tinku did in the last 3 days alone

1 day = 1/15 of the work

3 days = 1/15 x 3 = 1/5 of the work


Find the amount of work Vicky and Tinku did together:

Amount of work = 1 - 1/2 - 1/5 = 3/10


Find the amount time they take to finish the work:

1 day = 1/12 + 1/15 = 3/20

Number of days needed = 3/10 ÷ 3/20 = 2 days


Find the total number of days needed to complete the work:

Number of days = 2 + 2 + 3 = 7 days


Answer: 7 days


Answered by bhatiamona
1

Answer:

Step-by-step explanation:

Work done by Raju in 1 day=>1/10

Work done by Vicky in 1 day=>1/12

Work done by Tinku in 1 day=>1/15

Initialy 3 of them work together for 2 days...

One of them leaves after that working for X days...

at last only Tinku remains n works for 3 days...

So

2*(1/10+1/12+1/15) + X*(1/12+1/15) + 3*(1/15)=1

Solving :x=2

Hence 2+2+3=7.

Total work was done in 7 days.

Similar questions