Rakesh completes 5/8 of a job in 20 days. How many more days will he take to finish the job
at his current rate?
Answers
Answered by
2
Answer:
32 days
Step-by-step explanation:
20 is 5/8 part
therefore 1/8 work needs
20/5=4 days
multiplying both sides by 8
8*1/8=8*4
1=32 days
Answered by
4
Answer:
5/8 of job Rakesh finishes in 20 days
So job remaining= 1-(5/8)= 3/8
5/8 job is finished in 20 days
1 (full) job will be finished in 20/(5/8) days
3/8 job will be finished in 20×(8/5)×(3/8) days
=12 days