Ram and Mohan can do a piece of work in 6days and 4days respectively. ram star the work and works for 2days alone. Then Mohan joins him. How long will it take them to finish the remaining work

Answers

Answered by Mohanaleela
4
Plz I don't know answer but I will give advise that is ask your question again
Answered by kartikeymishra
31
Ram can do a piece of work in one day=1/6.
Mohan ". ". ". ". " =1/4.
They can do together in one day =1/6+1/4
=5/12
Ram work =1/6×2=1/3.
Remaining work =1-1/3=2/3.
Let they can do in x day
Therefore, x×5/12=2/3
x=12×2/5×3
x=8/5.
Tell me it is correct or not