Ram can do 2/5 part of a piece of work in 9 days. Remaining work is done with the help of Mohan in 6 days. Find the number of days in which Mohan will finish the work alone.
Answers
Answered by
0
Step-by-step explanation:
Ram can do 2/5th work in 9 days.
Ram can do whole work in 9*5/2= 45/2 days.
Ram and Mohan can do 3/5 work in 6 days.
they can do complete work = 6×5/3= 10 days.