Math, asked by Aswani12345, 11 months ago

Ram can do a piece of work in 12 days. Amir can do the same work in 6 days. if they work together, in how many days will they finish the work.

Answers

Answered by Devine36
7
(12×6)/18= 4 days will be the answer
Answered by rachnapatel
20
I hope that it will helps you.