Ram can do a piece of work in 20 days, while Shyam can do it in 30 days . if both of them work together, in how many days will they be able to finish the work.
Answers
Answered by
1
Answer:
The time taken by them to finish the work together is 12 days.
Step-by-step explanation:
We will solve this question using Unit Method.
Let the total work be 1 unit.
Time taken by Ram to do 1 unit work = 20 days
Work done by Ram in 1 day = 1/20 units
Time taken by Shyam to do 1 unit work = 30 days
Work done by Shyam in 1 day = 1/30 units
Work done by them together in 1 day
= 1/20 + 1/30
= (30 + 20)/ 20*30 By taking LCM
= 50/600 units
Therefore, number of days required by them to complete 1 unit work
= 600/50 days
= 60/5 days
= 12 days