Ram can finish a piece of work in 20 days while ramesh can do it in 12 days . Ramesh worked on it for only 9 days. Now ram can finish the remaining work in
Answers
Answered by
10
Answer:
5 days
Step-by-step explanation:
Given Ram can finish a piece of work in 20 days while ramesh can do it in 12 days . Ramesh worked on it for only 9 days. Now ram can finish the remaining work in
In 12 days Ramesh can finish one full piece of work.
Therefore in 9 days work done will be 9/12 = 3/4
In 9 days Ramesh has completed 3/4 piece of work
So Remaining piece of work is 1 - 3/4 = 1/4
Now Ram can do one piece of work in 20 days.
So 1/4 piece of work will be completed in 1/4 x 20 = 5 days
Now ram can finish the remaining work in 5 days
Answered by
0
Answer:
in 5
Step-by-step explanation: