Math, asked by HamsaThalvar2121, 1 year ago

Ram completes 60% of a task in 15 days and then takes the help of rahim and rachel. Rahim is 50% as efficient as ram is and rachel is 50% as efficient as rahim is. In how many more days will they complete the work?