Ram,shyam and hari can do a work in 20,30 and 60days respectively.In how many days, Ram would complete the work if Shyam and Hari help Ram working alternately?
Answers
Answer:
14 days
Step-by-step explanation:
Ram can complete work in 20 days, daily progress= 1/20
Shyam can complete work in 30 days, daily progress= 1/30
Hari can complete work in 60 days, daily progress= 1/60
Ram gets help from Shyam and Hari alternately:
day 1- they complete:
- 1/20+1/30= 5/60 of work
day 2- they complete:
- 1/20+1/60= 4/60 of work
Every 2 days they complete:
- 5/60+4/60= 9/60 of work
To complete full work they need:
- 2*60/9= 13.33 days so roughly 14 days
Answer: Ram would need 14 days to complete work
Answer:
15
Step-by-step explanation:
Amount of work ram can do in 1 day = 1/20
Amount of work shyam can do in 1 day = 1/30
Amount of work hari can do in 1 day = 1/60
ram is working alone and every third day shyam and hari is helping him
Work completed in every three days = 2 × (1/20) + (1/20 + 1/30 + 1/60) = 1/5
So work completed in 15 days = 5 × 1/5 = 1