rama can do a piece of work in 10 days and shyam in 13 days. if both of them work together, how long will they take to finish the work ?

Answers

Answered by abhaythommanchirayil
2

Number of days taken by Rama = 10

Work some by Rama in a day = 1/10

Number of days taken by Shyam = 13

Work done by Shyam in a day = 1/13

Work done by both of them

Work done by both of them together in a day = 1/10 + 1/13

Work done by both of them together in a day = 1/10 + 1/1310+13/130------------>23/130

Number of days taken by both = 130/23