Math, asked by arun2vp, 6 months ago

raman can do a piece of work in 48 days niwas can do the same work in 56days.they started the work jointly after 12 days chiru is joint them and completed the remaining work in 9days.all of the tottal paid 13440 what is the share of niwas?​

Answers

Answered by amitnrw
2

Given : Raman can do a piece of work in 48 days, while Niwas can do the same work in 56 days

They started the work jointly after 12 days Chiru also joined them and thus all of them completed the remaining work in 9 days.

All of them were paid total Rs. 13440.

To Find :  What is the share of Niwas

Solution:

Raman and niwas worked for 12 + 9 = 21 days

chiru worked for 9 days

Raman can do a piece of work in 48 days,

=> 1 day work  =  1/48

=> Raman  21 days works = 21/48   = 7/16

Niwas can do a piece of work in 56 days,

=> 1 day work  =  1/56

=> Niwas  21 days works = 21/56   = 3/8

Paid for total work  = 13440

=> for 3/8 work paid = (3/8) * 13440

= 5040

Share of Niwas = 5040 Rs

Learn More:

with P starting the work, working on alternate days P and Q can

brainly.in/question/12303996

With p starting the work, working on alternate days, p and q can ...

brainly.in/question/12364364

Similar questions