Ramesh and Sushil can finish a piece of work in 20 days and 25 days respectively. They both work together for 5 days and then Sushil goes away. In how many days will Ramesh complete the remaining work?
Answers
Answered by
9
please see the attachment.
Attachments:
Answered by
6
Answer:
11 days.
Step-by-step explanation:
In the question,
Time taken by Ramesh to finish a piece of work = 20 days
Time taken by Sushil to finish a work = 25 days
Time for which they worked together = 5 days
Sushil left after = 5 days
So,
One day work of Ramesh is,
One day work of Sushil is,
So,
Work done in 5 days is given by,
Therefore, Remaining work is given by,
Now, as the Sushil left the remaining work was done by Ramesh,
Time taken by Ramesh for the remaining work is,
Therefore, the remaining work will be completed in 11 days by Ramesh.