Ramesh can finish a piece of work in 12 days while Suresh can do it in 15 days if both work together ,what will they to do the work
Answers
Answered by
2
Answer:
Step-by-step explanation:
A can work 1/12 in one day
B can 1/15 in one day
If they work together 1/12 + 1/15 = 3/20
Total work consider as one part then
3/20 * x = 1
x = 6.6666
Days cannot be in decimals so it takes 7 days if they work together