Math, asked by harika279, 1 day ago

Ramit can finish his work in 25 days working 8 hours a day if he wants to finish the same work in 20 days how many hours should he work in a day?​

Answers

Answered by XxItzCuteAkshayxX
3

If a work is completed in work  days by working  hours per day and the same work completed in work  days by working  hours per day ,

Then,

=n_1  X h_1 =n_2  X  h_2\\

Given,

=n_1\\ = 25 days

=h_1 = 8 hours per day

=n_2 = 20 days

Thus ,

=25 X 8 = 20 X h_2

=h_2 = \frac{200}{10} = 10

→ ║hope hope it was helpful  ║ ←

→ ║mark as brainleist answer║ ←

→ ║drop 20 thanks target       ║←