Math, asked by cuteee26, 11 months ago

Ramit can finish is work in 25 days working 8 hours a day if he wants
to finish the same work in 20 days how many hours should we work in a day

Answers

Answered by ladugouda2
1

Answer:

10hr per day

Step-by-step explanation:

Ramit works per day - 8 hours

He work 25 days by 8 hours per day

total hour work in 25 day= 8hrs x 25 days= 200 hours

if Ramit complete his work in 20 days

total works will do= 200/20=10 hours