Ramita can complete 1/20 part of a work in one day. how long will she take to complete the work?
Answers
Answered by
39
Answer:
20 days
Step-by-step explanation:
Ramita complete 1/20 work in 1 day
Ramita will complete 1 work in =
1/(1/20) = 20 days
Answered by
11
Answer:
20 days
Step-by-step explanation:
rasmita complete 1/20 in 1 day
Rasmita will complete 20 days to complete the work
therefore she take 20 days to complete work