Math, asked by SATHVIKA3035, 5 months ago

Ramu can do a piece of work in 30 days Harry can do same work in 60 days how long will they take to do it​

Answers

Answered by dixitpriya929pczt5f
0

Answer:

Ram takes 20 days to complete a piece of work.

Shyam takes 30 days to complete a piece of work.

Ram completes (1/20) of a piece of work in 1 day.

Shyam completes (1/30) of a piece of work in 1 day.

Together R and S complete (1/20) + (1/30) = (1/12) of a piece of work in 1 day.

(1/12) of a piece of work - 1 day

(12/12) of a piece of work - (12/12)/(1/12) = 12 days.

R and S take 12 days to complete a piece of work when they work together.