Math, asked by natraj9, 4 months ago

ran can do a piece of work in 4 hrs and shyam can do the same work in 8 hrs. How log will the take to do the work jointly?​

Answers

Answered by Anonymous
2

Answer:

Answer:Ram completes his work in 20 days.

He completes 1/20 th work in one day.

Shyam completes his work in 30 days.

He completes 1/30 th work in one day.

If both of them work together they can complete ( 1/20 + 1/30 ) th work in one day.

1/20 + 1/30 = 50/600 i.e. 8.3333% work completed in one day.

1 day : 8.3333% work = ? : 100% work

100/ 8.3333 = 12 days

So together, they can complete a piece of work in 12 days...

hope it helps uh...

Step-by-step explanation:

MissInvisible...✌️