Math, asked by tiwariabishek21, 9 months ago

Ran can do piece of work in 8 days.he worked for 6 days and left.if hari finish as the reamining work how much work is done by hari
?

Answers

Answered by rohitrs0908
4

Answer:

Step-by-step explanation:

Let the total work be 1

Work done by Ram in one day = 1/8

Work done by Ram in six days = 6/8 = 3/4

Remaining work = 1-3/4 = 1/4

Work done by Hari = 1/4 of total work.