Math, asked by kumarparveen4365, 4 days ago

Rani can do 1\4 of a work in 4 days and Vani cab do 1\5 of the work in 4 days. If both work together, how long will they take to complete the entire work?

Answers

Answered by garimachandurkarthd
4

Answer:

Answer: Rani completes1/4 of work in 4 days. 1/4×4=work done by her in 1 day=1/16. if both work togethr...in 1 day,they complete 1/20+1/16=16/320+20/320 = 36/320 = 9/80.