Ranjan can do a piece of work in 24 days while Amit can do it in 30 days .In how many days can they complete it,if they work together?
Answers
Answer:
13⅓ Days
Step-by-step explanation:
Ranjan can do 1/24 of work in 1 day. While Amit can do 1/30 of work in 1/30.
So Amount of work done by both of Them is 1/24 + 1/30
= 24+30/720
54/720 = 3/40
Reciprocal of 3/40 Is 40/3
40/3 = 13 ⅓ Days.
Therefore, If Ranjan and Amit can do work together then they can complete that work in 13⅓ Days.
Hope it helps
If so then pls mark as brainliest answer
Thankyou ✌️
Given:
Ranjan can do a piece of work in 24 days.
Amit can do it in 30 days.
To find:
In how many days can they complete it, if they work together.
Solution:
Ranjan can do a piece of work in 24 days.
Work done by Ranjan in 1 days =
Amit can do a piece of work in 30 days.
Work done by Amit in 1 days =
Work done by both Ranjan and Amit together in 1 day is, + =
Work done by both Ranjan and Amit together in 1 day =
Total number of days required to finish the work by Ranjan and Amit is,
=
Total number of days required to finish the work by Ranjan and Amit =
Final answer:
In 13.4 days Ranjan and Amit can complete a piece of work, if they work together.