Ranjith can complete a task in 25 days while Anji can finish it in 20 days. They work together on the task for 5 days and then Ranjith leaves. In how many days will Anji finish the remaining work?
A) 15 days B) 10 days C) 11 days D) 9 days
Answers
Answered by
2
Hence, option C is the correct answer.
11 DAYS..
Answered by
0
Heyy Mate!!✌✌
Anji finish the remaining work in 11 days.
Please Mark it as Brainliest answer and follow me.