Ravi and Rishi can do a piece of work in 24 days , Rishi and Ronit in 30 days , Ronit and Ravi in 40 days. They all work together for 4 days and then, Ravi left, In how many days can Rishi and Ronit finish the remaining work?
STEP BY STEP EXPLANATION PLEASE
Answers
Answered by
1
Step-by-step explanation:
(Ravi and Rishi)’s 1 day’s work =1/24
(Rishi and Ronit)’s 1 day’s work = 1/30(Ronit and Ravi)’s 1 day’s work = 1/40
On adding, we get
2 (Ravi + Rishi + Ronit)’s 1 day’s work = (1/24 + 1/30 + 1/40) = 1/10
So,(Ravi + Rishi + Ronit)’s 1 day’s work = 1/20
So, they all together can finish the work in 20 days.
Ravi’s 1 day’s work = [(Ravi + Rishi + Ronit)’s 1 day’s work] - [(Rishi + Ronit)’s 1 day’s work] =
(1/20 -1/30 ) = 1/60
So, Ravi alone can finish the work in 60 days.
Similarly, Rishi’s 1 day work = (1/20 - 1/40) = 1/40
So, Rishi alone can finish the work in 40 days
And Ronit’s 1 day work = (1/20- 1/24) = 1/120
So, Rishi alone can finish the work in 120 days.