Math, asked by Mohanish98, 9 months ago


Ravi can pack 54 pens or 72 pencils by working 6 hours a day and Sunil can pack 45 pens or 70 pencils by working 5 hours a day. They received an order of packing 4500 pens and 5600
pencils. If they work together for 10 hours a day then in how many minimum days can they deliver the order?
Pick ONE option
A) 60 days
B) 50 days
C) 55 days
D) 45 days​

Answers

Answered by amitnrw
3

Given :  Ravi can pack 54 pens or 72 pencils by working 6 hours a day and Sunil can pack 45 pens or 70 pencils by working 5 hours a day. They received an order of packing 4500 pens and 5600  pencils

To find : working together for 10 hours a day then in how many minimum days can they deliver the order

Solution:

Ravi can pack 54 pens or 72 pencils by working 6 hours a day

=> Ravi can pack 9 pens or 12 pencils by working 1 hours a day

=> Ravi can pack 90 pens or 120 pencils by working 10 hours a day

Sunil can pack 45 pens or 70 pencils by working 5 hours a day.

=> Sunil can pack 9 pens or 14 pencils by working 1 hours a day.

=> Sunil can pack 90 pens or 140 pencils by working 10 hours a day.

Ravi & Sunil both can pack 90 pens in a day

but sunil can pack 140 pencils in day

Let sunil pack all the  5600 pencils  = 5600/140  = 40 Days

Now 4500 pens can be packed in 4500/90  = 50 Days

45 Days by Ravi  & 5 Days by Sunil

Sunil Total days = 40 + 5  = 45  Days

Hence They can deliver the project in  45 Days  

Option C is correct

Learn More:

Atul, Bhaskar and Chetan can complete a work in 10, 20 and 25 ...

https://brainly.in/question/9204706

Amit can complete a piece of work in 2.25 days. Badri takes double ...

https://brainly.in/question/7554548

Similar questions