Ravi is four times more efficient than ram and can finish his work in 10 days. if they started working at the same time then in how many days they will complete the work together
Answers
Answered by
4
Answer:
no.of days they will complete the work together =8 days
Answered by
0
Ravi and Ram can complete the work together in 3 1/3 days
Given:
Ravi is four times more efficient than Ram
Ram can finish a work in 10 days
To find:
If they started working at the same time then, the number of day they will take to complete the work
Solution:
Given that Ram can complete a work in 10 days
⇒ The work can be completed by Ram in one day =
Ravi is 4 times more efficient than
⇒ The work can be done by Ravi one day = =
If they started working together
The work can be done by both in 1 day = =
If they can do th of the work in 1 day
The number of days to complete 1 work = = = 3 1/3 days
Ravi and Ram can complete the work together in 3 1/3 days