Ravi takes 6 days to complete a job. Shyam takes 12 days to complete the same job.
work together how many days they will take to complete the job?

Answers

Answered by BrajeshChandra
0

Step-by-step explanation:

4 days is the correct answer

PLEASE FOLLOW ME

Answered by minfdweif
1

Answer:

4 days

Step-by-step explanation:

1/6 + 1/12 = 1/4