Ravi takes 6 days to complete a job. Shyam takes 12 days to complete the same job.
work together how many days they will take to complete the job?
Answers
Answered by
0
Step-by-step explanation:
4 days is the correct answer
PLEASE FOLLOW ME
Answered by
1
Answer:
4 days
Step-by-step explanation:
1/6 + 1/12 = 1/4